Collapsed Sheet Pile on Jalan Puri Kembangan Repaired

The West Jakarta Water Resources (SDA) Sub-agency repairs the collapsed sheet pile of the Shelter Puri Connecting Channel on Jalan Puri Kembangan, Kembangan Selatan Urban Village, Kembangan Sub-district.

It is carried out because stone rubble has blocked the water flow

Kembangan Sub-district SDA Executing Unit Head, Mulyadi expressed the repair was conducted up to 2.3 meters high with a bottom width of 1.3 meters and a top width of up to two meters.

"It is carried out because stone rubble has blocked the water flow," he expressed, Thursday (9/21).

Collapsed Sheet Pile Repairs in Cawang Finally Completed

It has been carried out since Tuesday (9/19) and is targeted for completion in two weeks ahead.

"To do it, we deploy eight personnel to the location," he stated.

Linked News
Popular News indeks
  1. Rano: Pancasila is the Big House for Indonesia's Diversity

    access_time02-06-2025 remove_red_eye526 personBudhi Firmansyah Surapati
  2. Transjabodetabek Bogor–Blok M Route and Corridor 13 Extension Begin Operations

    access_time05-06-2025 remove_red_eye396 personDessy Suciati
  3. Friendly Countries' Ambassadors Participate in Famtrip to Seribu Islands

    access_time05-06-2025 remove_red_eye396 personAldi Geri Lumban Tobing
  4. S. Jakarta Mayor: Idul Adha is a Moment to Enhance Compassion Among One Another

    access_time06-06-2025 remove_red_eye272 personTiyo Surya Sakti
  5. No Odd-Even Restrictions in Jakarta on June 6-9, 2025

    access_time03-06-2025 remove_red_eye271 personAldi Geri Lumban Tobing

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik